hi all,
i am a pp consultant. and handling a steel company support. Company is having Mill products implement. Honestly i do not know anything about mill products.
I want help from you. I have following issues :
- where can i get complete process steps for MTO in mill products.
- if any one can send me configuration steps that will help me lot in support properly.
- After production I found finish material as per unit weight more than charging qty. How can here adjust difference?
- We have no identification link with finish production order to internal Production order
- I have 1 billet 12.000 Mtr. Its length how can divide 2 or three length?
- Cold bar & Miss Roll scrap material code after allocated in routing operation. Material allocation cannot copy in production order. They are come by default first operation
please help to resolve the issues.